Harlingen Consolidated Independent School District is making progress on upgrades throughout its campuses, all of which were made possible with the passing of the tax ratification in September 2015.
HCISD Academies
Media Arts and Communications Academy
Upgrades are being made to the former Memorial MS Band Hall Building to house the Media Arts and Communications Academy (MACA). Includes two large classroom lab studios and one large TV Studio. Project Completion Timeline: August 2017
MACA
The paint has gone up in the room that will house the KHGN TV Studio.
MACA
Maintenance Crews have completed demolition work on the floor tiles and door openings in the block walls. Currently working with them for additional drainage and flat work proposal.
Apprenticeship Academy
Electrical and Plumbing Academy at HHS – Alpha Construction has commenced demolition work. Maintenance will assist in renovation work.
Transportation, Distribution and Logistics
HHS Autobody and Paint Shop Improvements – Upgrades have been made to Auto Body and Paint Shop via Texas Workforce Commission grant award. The maintenance department has performed additional clean-up and painting. A ribbon cutting has been scheduled for June 14, 2017.
Transportation, Distribution and Logistics
In-house crews are completing electrical improvements. Electricians have run heavy conduit from exterior panels to new panel location. Equipment recently installed is operational and in use. Contractors involved in improvements have completed tasks.
Transportation, Distribution and Logistics
Automotive Technology at HHS – Alpha Construction is completing ceiling insulation demolition and will shortly begin painting of ceiling deck and walls. An additional car lift will be installed by vendor.
Additional Progress
Welding Technology – Electrical upgrades are being engineered for additional welding machines. Painting work will also be required. Teacher Academy, Fire Fighter Academy, and Dental Lab – Painting and new ceiling tiles are required. These projects will be ready for 2017-2018 school year.
HCISD Sports Facilities
Boggus Stadium
Upgrades are being made to Boggus Stadium with the addition of safety hand rails. The contractor is scheduled to mobilize to the site by June 12, 2017.
Baseball and Softball Field Upgrades
Upgrades will be made to bleachers, parking, and restrooms at Dixieland and Keys high school fields.
Baseball and Softball Field Upgrades
Design Timeline: Schematic Design Phase February – April 2017, Design Development April – May 2017, Construction Documents June – July 2017. Bidding Phase June 2017, Project Award Early August 2017. Estimated completion 6 months.
Baseball and Softball Field Upgrades
Final floor plan designs for restroom/concession buildings have been finalized. Parking requirements including concrete asphalt are now established.
Middle School Athletic Tracks
Track upgrades happening at Coakley MS, Gutierrez MS, and Vela MS. Coakley and Vela tracks have been completed. The contractor has completed sub-grade and base preparation at Gutierrez MS. Pictured: Coakley hydro-mulched grasses are taking hold with the assistance of the sprinkler system. Project Completion: July 2017
Middle School Athletic Tracks
Gutierrez MS – existing construction status just after recent rains
Middle School Athletic Tracks
Gutierrez MS – installation of drainage structures
Additional Campus Upgrades
Parking Lot Improvements
Parking lot improvements taking place at HHS, Vernon MS, and Crockett Elementary School. The contractor will mobilize June 2, 2017. Work will begin early on at the High School on the north road and southern student lot. Pictured: Crockett existing parking area conditions. Project Completion Timeline: August 2017
Parking Lot Improvements
Pictured: Crockett existing area to receive concrete bus turn-around.
Parking Lot Improvements
Work has started early on at the High School on the north road and southern student lot.
Parking Lot Improvements
Pictured: Vernon MS south teacher’s lot to be reconstructed.
Electrical Panel Upgrades
Electric gear and panel upgrades happening at Harlingen South, Lamar and Stuart Place Elementary Schools.Work is scheduled to take place in mid to late July 2017, into early August. Project Completion Timeline: August 2017
A/C Upgrades
A/C Upgrades and replacements are happening at Harlingen High School. The contractor has pre-wired all wings with controls wiring. Control valves have been installed. Foundation construction for new chiller is complete. Project Completion Timeline: August 27, 2017
Re-Roofing and A/C Upgrades
Re-Roofing and AC Replacements at Travis Elementary/Classroom Wing at Zavala Elementary.
Pictured: Travis roof cap sheet installation is at about 95%. One RTU is in place and is operational. Three additional steel support frames are pending design adjustment.Demolition of interior ceilings and ducts is scheduled to begin on June 6, 2017. Project Completion Timeline: August 11, 2017
Re-Roofing
Pictured: Zavala roof base sheet is complete. Additional re-roofing projects include metal roof replacement at Coakley MS, Austin and Sam Houston Elementary Schools classroom wings as well as Bonham, Crockett, and Treasure Hills Elementary School Multi-Purpose Buildings. Project Completion Timeline: December 2017.
Lighting Upgrades at all Elementary Campuses
The district will be replacing T-12 Lamps and old metal halides with LED fixtures at Austin, Bonham, Bowie, Crockett, Dishman, Jefferson, Lamar, Long, Milam, Rodriguez, Sam Houston, Stuart Place, Travis, Treasure Hills, Wilson, and Zavala Elementary Schools as well as lights at HHS and HHS South Gymnasiums.
Lighting Upgrades at all Elementary campuses
Bowie and Austin Elementary schools are complete. Bonham lacks the stage area. The contractor is currently working at Jefferson and Lamar. Project Completion Timeline: November 2017
Metal Canopies
Roof canopy structure to be installed at Ag Farm as well as entry canopy walkway at Lee Means Elementary School. Project Completion Timeline: October 2017
Middle School Surveillance Cameras
Coakley, Gutierrez, Vela, and Vernon Middle Schools to receive surveillance camera systems. Will recommend award at the June School Board Meeting. Project Completion Timeline: November 2017.
Metal Canopies
Project architects have finalized the design and construction drawings and project is in bidding phase. Will be advertised in June 2017. Bids are to be received on June 29, 2017. Recommendation will be made at the August school board meeting.
By: Marifer Quevedo
In the summer of 2013, the Texas Legislature passed House Bill 5, an initiative calling for a complete restructure of high school student graduation plans and the introduction of a new career and technical education (CTE) course development option. The Harlingen Consolidated Independent District, in line with the district strategic and district of innovation plans, has masterminded and launched six academies featuring CTE courses, where approximately 4,300 Harlingen students will embark on new career pathways in August 2017.
With funds made possible through the Tax Ratification Election (TRE) passed in September 2015, maintenance and construction crews have been diligently demolishing, painting, and upgrading the district’s facilities to meet industry related standards. The district has allotted $1.2 million for the three year CTE expansion plan.
The first year (2016-2017) consisted of a methodical planning period where the budget was set aside while the district fostered local partnerships with various community leaders including the Harlingen Fire Department, Spawglass Construction, Valley Baptist Medical Center, Harlingen Medical Center, and local auto mechanics.
The second year (2017-2018) will mark the launch of the new academies housed at Cano Freshman Academy, Harlingen High School, and Harlingen High School South. Of the reserved TRE budget, $625,000 has been designated this year for furniture, equipment, supplies, welding machines, and construction costs of the facilities.
“We have good people with great vision in the district. All levels understand the importance of investing in our children, not only the current students, but also the future children coming up the pipeline,” says Director of Career and Technical Education Raul Alvarez. “I have sat through numerous planning meetings and have never, not once, encountered any form of hesitation that this is the right path for our district.”
After extensive electrical and lighting upgrades, interior and exterior remodeling, an A/C replacement, and security installation, the former Memorial Middle School Band Hall has been transformed into the Media Arts and Communications Academy (MACA). The inside classrooms have been converted into state-of-the-art audiovisual and graphic arts collaboration work centers, audio and editing rooms, the KHGN studio, and the district’s print shop.
“The goal is for our students to enter the pathway in 9th grade at Cano, where they learn and develop foundational skills in both AV Production and Graphic Arts,” explains Alvarez. “Students will then transition to their comprehensive high schools where they continue to perfect their skills in these areas.”
By their senior year, students will be transported from their high school to the MACA, where they will engage in realistic learning experiences in a cutting edge environment that is aligned to industry standards.
“We have to think about the spectrum of life and what students need in order to be college and career ready,” says Alvarez. “We know major industries are coming down to the Valley’s market to capitalize on the low cost of living. We know they need skilled individuals so we need to empower our schools. At 17, we want our students to graduate with more tools in their pockets to give them a competitive edge and to help them develop themselves and their passions.”
In effort to aid in the expansion of CTE opportunities for students, House Bill 5 allows school districts the ability to issue teaching permits to individuals who do not hold a teaching certificate, but who the district regards as highly qualified industry experts to teach these technical courses. Candidates need to meet a determined set of criteria including: professional work experience, relevant industry licenses, background checks, classroom management training, and sufficient expertise to provide instruction necessary to meet the Texas Essential Knowledge and Skills (TEKS).
Students enrolled in the CTE academies will be able to learn first-hand from experts and specialists in their chosen fields. They will have the opportunity to graduate not only with authentic, hands-on experience, but also with possible postsecondary credit, an associate’s degree, or an industry-recognized certification.
The state of Texas requires for Texas schools to include at least one of 16 career and technical industries into its programs. HCISD currently incorporates 15 out of these 16 programs of study.
The third year of the CTE expansion plan (2018-2019) will consist of improvement of current academies and the introduction of additional academies in fields including HVAC (heating, ventilation, and air conditioning), police and EMT, business finance and marketing, culinary arts, aviation, and diesel mechanics.
“We are investing in our students so they leave our district with something valuable,” says Alvarez. “We need them to be more than just a number and be prepared to succeed in whichever direction they may go.”